Cricket Creek Forest Preserve Levee Maintenance and Habitat Improvement Project

 

Summary of Work

Cricket Creek Forest Preserve in Addison was likely prairie until European settlement, when it started transforming into agricultural fields. The DuPage Forest Preserve District acquired the first 40 acres in 1974 and made subsequent purchases through 2016, eventually transforming a flood-prone housing development into a forest preserve.

The Forest Preserve District is conducting levee maintenance and habitat improvements at Cricket Creek Forest Preserve beginning in late January 2020 and continuing through summer 2020.

 

Status

The Forest Preserve District has hired Applied Ecological Services and its subcontractor, Homer Tree Service, to conduct levee maintenance and habitat improvements at Cricket Creek Forest Preserve beginning the week of Jan. 27, 2020. During the winter, crews will remove all brush and trees from the levee system and remove invasive trees and brush from the wetlands and natural areas. This work will finish by late April 2020.

After the levee maintenance work is done, these areas will be seeded in spring and summer with native cover to better stabilize the slopes. Newly seeded areas will be rough mowed several times over the growing season to minimize the return of brush and help establish the grass.

In total, the District will enhance approximately 21 acres. The habitat improvement portion of the project will create a larger and more functional restored wetland landscape. Native wildflowers and grasses will increase through seeding and planting, resulting in a healthier and more sustainable habitat along Salt Creek.

The contractors will provide maintenance on the levee for 6 years.

 

Funding

The project costs approximately $429,000, with $338,000 funded from DuPage County Stormwater Management wetland mitigation revenue and $91,000 from the Forest Preserve District budget.

 